Innovative remote operating lifting tool for East Anglia ONE

Designed to be remotely operated, TWD's innovative lightweight tool weighs less than 25t, but is capable of lifting jackets up to 1,600t.

The last jacket foundation for offshore wind farm East Anglia ONE has been installed, thanks in part to an innovative lifting tool designed specifically for the purpose by Temporary Works Design (TWD).

Under its contract with ScottishPower Renewables, Van Oord was responsible for the transportation and installation of all 102 foundations, the largest number ever installed for an offshore wind farm. To complete the installation work efficiently Van Oord utilised specifically designed tools which included a pile template for the three anchoring piles on the foundations and a lifting tool for the jackets.

Once the anchoring piles were in place the jacket could be installed from the vessel. Most of the work was carried out in seas deeper than 40m where the wind, current and sea state often produce challenges when lifting and placing the jackets.

For this work an innovative lifting tool was specifically designed by Temporary Works Design (TWD). The lightweight tool weighs less than 25t, but is capable of lifting jackets up to 1,600t. It is designed to be remotely operated, without the need for any personnel being on the top of the jacket for connecting or releasing. Two tools were delivered, the second one having a more developed design which included the ability to change the lift connection dimensions for use on other projects.

TWD has vast experience in the design of offshore lifting tools, much of which was incorporated into the design of this lightweight Jacket Lifting Tool, in which operational safety, speed and redundancy were seen as the main objectives.

Arnoud Kuis, Director of Offshore Wind at Van Oord, “Thanks to our ingenious working methods, the expertise of our project team and close cooperation with our partners and our client, we succeeded in installing all jacket foundations for wind farm East Anglia One smoothly and safely. We are proud to contribute to the UK’s energy transition.”

With a total of 102 Siemens 7 MW wind turbines the wind farm will eventually deliver a total of 714 MW, once the wind farm becomes operational in 2020. This is the equivalent of supplying more than 630,000 British households with green electricity.

Latest Press Releases

BANEDANMARK CHOOSES FUGRO’S RILA SYSTEM TO SURVEY THE DANISH RAIL NETWORK

Banedanmark has awarded Fugro a 4-year framework agreement for train-borne lidar scanning of its inf... Read more

FUGRO’S TARGETED APPROACH SECURES SECOND SEEP HUNTING SUCCESS OFFSHORE MALAYSIA

Fugro has successfully completed the second of three Malaysian seep hunting and geochemical campaign... Read more

SP ENERGY NETWORKS UTILISES FUGRO’S VIRTUAL TECHNOLOGY TO MODEL UK ELECTRICITY GRID IN 3D

The most advanced 3D digital modelling of the UK's electricity grid will be launched by electricity ... Read more

FUGRO SEEP HUNTING SUCCESS OFFSHORE MALAYSIA

Fugro has successfully completed the first of three Malaysian seep hunting and geochemical campaigns... Read more

KONGSBERG hydroacoustic and bridge technology chosen for new South African Navy survey vessels

Kongsberg Maritime, through its Cape Town-based business partner Unique Group, has been selected to ... Read more

Boskalis expands market position

Boskalis expands market position in marine survey through acquisition horizon. Royal Boskalis West... Read more

View all